Equipment Commissioning; Check Before Power On; Power On - Goodwe MS Series User Manual

Grid-tied pv inverter 5-10kw
Hide thumbs Also See for MS Series:
Table of Contents

Advertisement

User Manual V1.1-2022-11-15

7 Equipment Commissioning

7.1 Check Before Power ON

No.
The product is firmly installed at a clean place that is well-ventilated and easy to
1
operate.
The PE, DC input, AC output, and communication cables are connected correctly and
2
securely.
3
Cable ties are intact, routed properly and evenly.
4
Unused ports and terminals are sealed.
The voltage and frequency at the connection point meet the inverter grid connection
5
requirements.

7.2 Power On

Step 1 Turn on the AC switch between the inverter and the utility grid.
Step 2 (optional) Turn on the DC switch between the inverter and the PV string.
Step 3 Turn on the DC switch of the inverter.
PV
For Australia only.
Inverter
DC Isolator
(Optional)
07 Equipment Commissioning
Check Item
AC Breaker
25
Grid

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Gw5000-msGw6000-msGw7000-msGw8500-msGw10k-ms

Table of Contents