User Manual V1.0-2022-08-30

7 Equipment Commissioning

7.1 Check Before Power ON

No.
The product is firmly installed at a clean place that is well-ventilated and easy-to
1
operate.
The PE, DC input, AC output, and communication cables are connected correctly and
2
securely.
3
Cable ties are intact, routed properly and evenly.
4
Unused cable holes are fitted using the waterproof nuts.
5
The electrical conduit holes are sealed.
The voltage and frequency at the connection point meet the inverter grid connection
6
requirements.

7.2 Power On

Step 1: Turn on the AC breaker on the ON-GRID side of the inverter.
Step 2: Turn on the AC breaker on the BACK-UP side of the inverter.
Step 3: Turn on the battery breaker between the inverter and the battery.
Step 4: Turn on the DC switch of the inverter.
07 Equipment Commissioning
Check Item
43