User Manual V1.0-2023-05-20
7 Equipment Commissioning
7.1 Check Before Power ON
No.
The inverter is firmly installed at a clean place that is well-ventilated and easy to
1
operate.
The PE cable, DC input cable, battery cable, AC output cable, and communication
2
cable are connected correctly and securely.
3
Cable ties are intact, routed properly and evenly.
The voltage and frequency at the connection point meet the inverter grid
4
connection requirements.
5
The door of the wiring compartment is locked.
6
All the upstream and downstream breakers are disconnected.
7.2 Power On
Step 1 Turn on the AC breaker of the inverter.
Step 2 Turn on the DC switch of the inverter.
Step 3 Turn on the battery breaker of the inverter.
07 Equipment Commissioning
Check Item
37