7 Equipment Commissioning

No.

7.1 Check Before Power ON

The product is firmly installed at a clean place that is well-ventilated and easy-to
1
operate.
The PE cable, DC input cable, AC output cable, and communication cable are connected
2
correctly and securely.
3
Cable ties are intact, routed properly and evenly.
4
(Optional) The SIM card is properly installed.
5
Unused cable holes are fitted using the waterproof nuts.
6
The electrical conduit holes are sealed.
The voltage and frequency at the connection point meet the inverter grid connection
7
requirements.

7.2 Power On

Step 1 Turn on the AC switch between the inverter and the utility grid.
Step 2 Turn on the DC switch between the inverter and the battery.
Step 3 (optional) Turn on the DC switch between the inverter and the PV string.
Step 4 Turn on the DC switch of the inverter.