Equipment Commissioning; Check Items Before Switching Power On; Power On - Goodwe HT Series User Manual

Grid-tied pv inverter
Hide thumbs Also See for HT Series:
Table of Contents

Advertisement

07 Equipment Commissioning

7 Equipment Commissioning

7.1 Check Items Before Switching Power ON

No.
The inverter is firmly installed in a clean place where is well-ventilated and easy to
1
operate.
The PE cable, DC input cable, AC output cable, and communication cable are connected
2
correctly and securely.
3
Cable ties are routed properly and evenly, and no burrs.
4
Unused ports and terminals are sealed.
5
The voltage and frequency at the connection point meet the on-grid requirements.

7.2 Power On

Step 1 Turn on the AC breaker between the inverter and the utility grid.
Step 2 Turn on the DC switch of the inverter.
PV
Check Item
Inverter
AC Breaker
2
DC Switch
34
User Manual V1.1-2023-12-14
1
Power
distribution
cabinet
Transformer
Grid

Advertisement

Table of Contents
loading

This manual is also suitable for:

Gw250k-htGw250kn-htGw225k-htGw225kn-ht

Table of Contents