User Manual V1.3-2024-01-25
7 Equipment Commissioning
7.1 Check Items before Power On
No.
The inverter is firmly installed in a clean place where is well-ventilated and easy to
1
operate.
The PE cable, DC input cable, AC output cable, and communication cable are connected
2
correctly and securely.
3
Cable ties are routed properly and evenly, and no burrs.
4
Unused ports and terminals are sealed.
5
The voltage and frequency at the connection point meet the on-grid requirements.
7.2 Power On
Step 1 Turn on the AC switch between the inverter and the utility grid.
Step 2 (optional) Turn on the DC switch between the inverter and the PV string.
Step 3 Turn on the DC switch between the inverter and the PV String.
PV
String
DC Switch
DC Switch
Check Item
Inverter
AC Switch
47
07 Equipment Commissioning
Utility Grid