Installation Checklist

General Checklist (Applies to all units)
The checklist listed below is a summary of the steps
required to successfully install a Commercial rooftop unit.
This checklist is intended to acquaint the installing
personnel with what is required in the installation process.
It does not replace the detailed instructions called out in the
applicable sections of this manual.
Important: This checklist does not replace the detailed
instructions called out in the applicable
sections of this manual.
☐ Check the unit for shipping damage and material
shortage; file a freight claim and notify Trane office.
☐ Verify that the installation location of the unit will
provide the required clearance for proper operation.
☐ Assemble and install the roof curb per the current
edition of the curb installation guide.
☐ Fabricate and install ductwork; secure ductwork to
curb.
☐ Install pitch pocket for power supply through building
roof. (If applicable)
☐ Rigging the unit.
☐ Set the unit onto the curb; check for levelness.
☐ Ensure unit-to-curb seal is tight and without buckles or
cracks.
☐ Install and connect condensate drain lines to each
evaporator drain connection.
☐ Remove the shipping hold-down bolts and shipping
channels from the supply and relief/return fans ordered
with rubber or spring isolators.
☐ Check all optional supply and relief/return fan spring
isolators for proper adjustment.
☐ Verify all discharge line service valves (one per circuit)
are back seated.
Main Electrical Power Requirements
☐ Verify that the power supply to the unit complies with
the unit nameplate specification. Refer to Main Unit
Power Wiring in the Installation chapter.
☐ Properly ground the unit.
☐ Inspect all control panel components and tighten any
loose connections.
☐ Connect properly sized and protected power supply
wiring to a field supplied/installed disconnect and the
unit (copper wiring only to the unit).
☐ Verify that phasing to the unit is correct (ABC).
☐ Turn the 1S1 fused switch inside the control panel off to
prevent accidental unit operation. (20-75T units only).
☐ Turn the 1S1 and 1S20 fused switches inside the
control panel off to prevent accidental unit operation.
(90-130T units only).
RT-SVX072D-EN
☐ Turn on power to the unit.
☐ Press the STOP button on the User Interface (2P1).
☐ Allow compressor crankcase heaters to operate for 8
hours prior to starting the refrigeration system.
Important: All field-installed wiring must comply with NEC
and applicable local codes.

Field Installed Control Wiring

☐ Complete the field wiring connections for the variable
air volume controls as applicable. Refer to unit
diagrams for guidelines.
Important: Note: All field-installed wiring must comply with
NEC and applicable local codes.
Requirements for Electric Heat Units
SEH_ Units (460–575V)
☐ Verify that the power supply complies with the electric
heater specifications on the unit and heater nameplate.
☐ Inspect the heater junction box and control panel;
tighten any loose connections.
☐ Check electric heat circuits for continuity.
SEH_ Units with 200V or 230V Electric Heat: (Requires
Separate Power Supply to Heater)
☐ Connect properly sized and protected power supply
wiring for the electric heat from a dedicated, field-
supplied/installed disconnect to terminal block 3XD5, or
to an optional unit-mounted disconnect switch 3QB4.

Requirements for Gas Heat Units

☐ Gas supply line properly sized and connected to the
unit gas train.
☐ All gas piping joints properly sealed.
☐ Drip leg installed in the gas piping near the unit.
☐ Gas piping leak checked with a soap solution. If piping
connections to the unit are complete, do not pressurize
piping in excess of 0.50 psig or 14" W.C. to prevent
component failure.
☐ Main supply gas pressure adequate.
☐ Flue Tubes clear of any obstructions.
☐ Factory-supplied flue assembly installed on the unit.
☐ Connect the 3/4" CPVC furnace drain stub-out to a
proper condensate drain.
Requirements for Hot Water Heat (SLH_)
☐ Route properly sized water piping through the base of
the unit into the heating section.
☐ Install the factory-supplied, 3-way modulating valve.
☐ Complete the valve actuator wiring.
Pre-Installation
15

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the IntelliPak 1 with Symbio 800 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Table of Contents

Save PDF