Siemens SIMATIC ET 200AL System Manual page 73

Distributed i/o system
Hide thumbs Also See for SIMATIC ET 200AL:
Table of Contents

Advertisement

8.2
PROFIBUS DP
8.2.1
Commissioning ET 200AL on PROFIBUS DP
Introduction
The commissioning of your distributed I/O system depends on the system configuration. The
following procedure describes the commissioning of the ET 200AL distributed I/O system on
a DP master.
Requirements for the ET 200AL distributed I/O system on a PROFIBUS DP
Note
Performing tests
You must ensure the safety of your plant. You therefore need to perform a complete
functional test and the necessary safety checks before the final commissioning of a plant.
Also plan the tests to include any possible foreseeable errors. This helps to avoid
endangering persons or equipment during operation.
Procedure
The following table shows the chapters/documents in which the required actions are
described.
Table 8- 2
Step
1
2
3
4
5
6
Distributed I/O system
System Manual, 02/2018, A5E31861578-AF
Requirements for the ET 200AL distributed I/O system on a PROFIBUS DP
Procedure
Mounting the ET 200AL interface module
Setting the PROFIBUS DP address on the
ET 200AL PROFIBUS interface module
Wiring the ET 200AL interface module
Configuring the ET 200AL interface mod-
ule
Turning on the supply voltage for the
ET 200AL interface module
ET 200AL interface module automatically
switches to RUN mode
See...
Section Mounting (Page 23)
IM 157-1 DP interface module
(https://support.industry.siemens.com/cs/ww/en
/view/89255073) manual, section Setting the
PROFIBUS DP address and terminating resis-
tor
Section Connecting (Page 28)
Section Configuring (Page 47)
IM 157-1 DP interface module
(https://support.industry.siemens.com/cs/ww/en
/view/89255073) manual
-
Commissioning
8.2 PROFIBUS DP
71

Advertisement

Table of Contents
loading

Table of Contents