Check The Running State; Check The Charging Function Of The Product - Alpha ESS SMILE-S5 Manual

Energy storage system
Hide thumbs Also See for SMILE-S5:
Table of Contents

Advertisement

70
Enter S/N, check code, license, create time, customer full name, contact number,
address, and click the save button. If you are an Australian installer, you will need to
fill in the Street (NMI), Suburb (NMI) and Postcode (NMI) fields and add a new Region
field, which has six fixed options (NSW, QLD, VIC, SA, TAS, WA). If SA is selected for
Region, two more fields are added which are Agent and NMI.
Fields that are not marked "optional" need to be filled in.
Click "Next" and go to Section 9.3 if the WiFi has not been configured.

9.5. Check the Running State

If you have completed commissioning as described in section 9.3.2, please ignore this
section.
You can also commission the system after WiFi configuration.
Please make sure the PV switch and battery breakers and all the breakers connecting
to the product are on.

9.5.1. Check the Charging Function of the Product

To make sure the system is installed and operating correctly, please set the system to
"Charging/Discharging Setting" by following the instructions below.
Step1
First click "Function" on the right-side bottom corner of
the Home page.
Then click "Charging and discharging setting"
COMMISSIONING