WIFI SETTING
Please set the safety standard appropriate for your country or purpose via APP or Web during pilot
run.
The safety standard must be set correctly
If you select a safety standard which is not valid for your country and purpose, it can
cause a disturbance in the energy storage system and lead to problems with the grid
operator. When selecting the safety standard, you must always observe the locally appli-
cable standards and directives as well as the properties of the PV system (e.g. PV system
size, grid-connection point).
• If you are not sure which safety standard is valid for your country or purpose, please
contact your grid operator for more information
NOTE:
When the safety regulation is set as AS4777.2, the secondary suboptions can be
selected according to the region or local grid company (Please refer to Appendix 2).
60
61
09

Commissioning

9.1 Checking Before Power-On

No.
Check Item
Mounting environment
1
Battery pack and
2
inverter mounting
WiFi mounting
3
4
Cable layout
5
Cable tie
6
Grounding
Switch and breakers status
7
Cable connections
8
Unused power
9
terminals

9.2 Check the Running State

Prerequisites
Before switching on the AC breaker between the inverter and the grid, check that the AC voltage on
the power grid side of the AC breaker is within the specified range.
Please select the acceptance of installation on site when the light intensity is strong.
Procedure
1. Ensure that the PV switch and battery breakers of the product and all the breakers connecting to
the product are OFF.
2. Check the grid-connected state of the product
Short press the power button on the left side of battery pack, then switch on the battery breaker
of battery pack.
Switch on the battery breaker which is located at the left of the inverter.
Switch on the PV switch which is located at the left of the inverter.
Switch on the external AC breaker between the grid and the inverter.
Set the operating parameters through the APP.
Wait about 3 minutes for the inverter to enter the grid-connected state, and observe the
indicators states on the display panel of the inverter. At this time, the following 4 LEDs ("SYS
TEM", "BATTERY", "METER", "COM") on the display panel is always on.
COMMISSIONING
Acceptance Criteria
The mounting space is proper, and the mounting
environment is clean and tidy, without foreign object.
The battery pack and inverter are mounted
correctly, securely, and reliably.
The WiFi module is mounted correctly,
securely, and reliably.
Cables are routed properly as required by the customer.
Cable ties are secured evenly and no burr exists.
The ground cable is connected correctly, securely, and
reliably.
The PV switch and battery breakers and all the
breakers connecting to the product are OFF.
The AC cable, PV cable, battery cable, and
communication cables are connected correctly,
securely, and reliably.
Unused power terminals are blocked by
watertight caps.

Advertisement

Table of Contents
loading

Table of Contents