5-10 Phase Sequence Measurement

1. Press
key to turn on the meter.
2. Press "WIRING" key to select 3P4W mode.
3. Connect the voltage test leads to the meter.
 Connect the red voltage test lead to the "U1" terminal.
 Connect the yellow voltage test lead to the "U2" terminal.
 Connect the blue voltage test lead to the "U3" terminal.
4. Connect the voltage test leads to the electrical equipment to be tested.
If possible, before connecting the voltage test leads and current probe
to the electrical equipment to be tested, take off the electrical
equipment's power.
 Connect the red voltage test alligator to the power line "A" phase.
 Connect the yellow voltage test alligator to the power line "B" phase.
 Connect the blue voltage test alligator to the power line "C" phase.
5. U1, U2 and U3 measured voltage must be greater than 30V, then press
and hold down "
annunciator is displayed. If connection wires is reverse phase, the "
annunciator is displayed. Release the "
measurement.
User Manual
CAUTION
" key. If connection wires is normal phase, the "
53
" key to exit this
"
"

Advertisement

Table of Contents
loading

This manual is also suitable for:

Pce-360

Table of Contents