5.8.1 Single-phase Wireless Meter Connection(for SG5.0RS-ADA)

Step 1 Disconnect the WiMeter-S from the voltage source and secure that it will not be
connected.
Step 2 Ensure that the conductors to be connected are free of voltage. Tighten the power
wires to terminal L and terminal N. Place the CT single-phase sensor around the phase wire
(L).
The arrow on the CT should always point to the load side.
Step 3 Cover the WiMeter-S with the insulating cover or contact protection of the power
distribution cabinet. Connect the power distribution cabinet to the power supply.
5.9

DRM Connection

In Australia and New Zealand, the inverter supports the demand response modes as speci-
fied in the standard AS/NZS 4777.
The following figure shows the wiring between the inverter and the external DRED.
table 5-4 Method of Asserting DRM
Mode
Asserted by Shorting Terminals on
Inverter
DRM0
R & C
5 Electrical Connection
Switch Operation on External
DRED
Close S1 and S5