Commissioning
3.1
Overview
The system commissioning process is:
•
Register the installation.
•
Commission the batteries.
Start the inverter, onboard, and initialise settings.
•
3.2
Commission Pylontech batteries
At the BoS, turn the BATTERY SYSTEM DC isolator OFF (down).
At the enclosure(s), turn the Battery Isolator(s) OFF (to right).
All batteries: toggle the Power switch ON.
On the Master battery, press and hold the red SW button until the
SoC LEDs flash, in sequence, on all connected batteries i.e. M, 2, 3, 4.
All connected batteries are now active.
3.3
Inverter start-up
3.3.1
INVERTER START-UP NOTES
The EMS LED labelling changed in 2019 to reflect changes in the way
the control system utilises the LEDs: newer EMS are labelled
NETWORK (was Wi-Fi) and BLUETOOTH (was 4G). The EMS are
otherwise unchanged.
Wait 10 minutes for the inverter to boot-up and advertise Bluetooth
(Bluetooth LED is flashing).
Ethernet connected systems will automatically connect to the
internet, if available, indicated by the NETWORK LED being
continuously ON.
Do not turn power OFF during start-up. This will delay start-up or may crash the system.
3.3.2
INVERTER START-UP PROCEDURE
# PROCEDURE
1. At the main switchboard, turn the Solar Supply Main Switch ON (Up)
2. At the enclosure(s), turn the Battery Isolator(s) ON (to left)
3. Switch the BATTERY SYSTEM DC isolator ON (up)
4. Turn the PV ARRAY DC isolator ON (clockwise to 12 o'clock)
5. Switch the BACKUP AC isolator ON (up)
6. Switch the BYPASS to Backup (down)
7. Switch the INVERTER AC isolator ON (up)
Installation Manual - Redback Smart Hy brid System - v2.0
Redback Technolo gies