2.4.3

INSTALLATION

Installation notes
The BE14000 Battery Enclosure is pre-wired for use with an AS5139 compliant SH5000 inverter.
Reduce heat load by installing out of full sun: ideally, the installation will be against a south facing external wall, and
under eaves.
Ensure the location is not flood prone from water across ground, nearby downpipes, or guttering.
Stand the enclosure on a stable, level surface. Use packers under feet if required.
Fasten the enclosure to a flat, structurally sound wall. Waterproofing will be affected if the enclosure is twisted or
damaged. Use spacers if required.
The enclosure features fan-assisted cooling. Ensure 150mm clear space either side. Do not block the cooling intakes
or exhaust vents.
Ensure at least 1000mm clear height is available above the enclosure (for inverter fitting).
Installation process
Place the enclosure in the required location: on the
floor; against the wall; 150mm clear space both sides.
Set the enclosure level. Use a spirit level as required.
Add packers under feet if necessary.
Check that the wall is flat. Use spacers as required to
ensure the enclosure does not distort when fastened to
the wall.
Six mounting points are provided, as shown at right.
Fix the enclosure to the wall using suitable fasteners.
Seal around the fasteners using the supplied sealant.
Preliminary installation is complete.
Installation Manual - Redback Smart Hy brid System - v2.0
Redback Technolo gies
19

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Be14000

Table of Contents