Commissioning - Xylem DIQ/S 281 Operating Manual

Universal transmitter for one digital sensor
Table of Contents

Advertisement

Installation
Start checklist and
system start
Starting the
system
52
Separating plate
Relais contact

3.10 Commissioning

Before starting the system, carry out the system check using the following
checklist. Always carry out the check:
 before the initial commissioning
 before any further commissioning if the system has been previously extended
or modified.
Start checklist:
1 Are all components correctly connected with each other (see
section 3.5.4, if necessary, section 3.6)?
2 Is the universal transmitter correctly connected to the power
supply (see section 3.8)?
3 Do the line voltage and line frequency agree with the data on
the name plate of the universal transmitter?
4 Is the sensor ready for measuring, e.g. a D.O. sensor filled
with electrolyte solution?
Switch on the power supply of the DIQ/S 281. As soon as the system is success-
fully initialized, the measured value display appears. With a sensor not yet pro-
viding any measurement values, "Init" appears temporarily:
Select your system language during the first system start. The
selected system language can be changed in the
Settings
menu at any time.
Auxiliary voltage output
Bridge
Valve control line
DIQ/S 281
Einstellungen/
ba76226e02
03/2023

Advertisement

Table of Contents
loading

This manual is also suitable for:

Wtw diq/s 281

Table of Contents