Installing an optional primary PCI riser board
Prerequisites
Before installing this option, be sure you have the following:
The components included with the hardware option kit
•
•
T-15 Torx screwdriver
Procedure
Back up all server data.
1.
Power down the server.
2.
Remove all power:
3.
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
Do one of the following:
4.
a. Extend the server from the rack.
b. Remove the server from the rack.
Remove the access panel.
5.
Remove the primary PCI riser cage.
6.
If needed, remove any expansion boards installed in the riser cage.
7.
Remove the existing riser board from the PCI riser cage.
8.