Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 50TL-480 and PVI 60TL-480
PROTECT0150
(MINI MCU
FAULT)
PROTECT0110
(BUS OVER
VOLTAGE
(FIRMWARE))
PROTECT0100
(LEAKAGE
CURRENT
SENSOR FAULT)
PVXREVERSE
(PV REVERSE
POLARITY)
PVXOVERCURREN
T
(PVX
OVERCURRENT
X=1,2,3)
PVXVOLTOVER
DOCR-071030-A (10/7/2022)
5.
Continue until you find the string that triggers the alarm. Trace
back the faulted string to find any leakage to Earth Ground.
Recommended solutions:
1. Restart inverter by turning both AC and DC switches OFF. Wait for
1 minute for all energy to discharge and turn both switches ON.
2. If inverter cannot clear fault, replace inverter.
Recommended solutions:
1. Restart inverter by turning both AC and DC switches OFF. Wait for
1 minute for all energy to discharge and turn both switches ON.
2. If inverter cannot clear fault, replace inverter.
Recommended solutions:
1. Restart inverter by turning both AC and DC switches OFF. Wait for
1 minute for all energy to discharge and turn both switches ON.
2. If inverter cannot clear fault, contact after-sales technical support
to replace Filter board or inverter.
Recommended solutions:
1. Turn DC Switch OFF.
2. Open Fuse holders to isolate PV source circuits.
3. Use meter to find out which PV source circuit is connected in
reverse polarity.
4. Correct PV source circuit connection.
Recommended solutions:
1. Check PV input Current.
2. Restart inverter by turning both AC and DC switches OFF. Wait for
1 minute for all energy to discharge and turn both switches ON.
3. If inverter cannot clear fault, replace inverter.
Recommended solutions
Page 107 of 131

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Solectria pvi 50tl-480Solectria pvi 60tl-480

Table of Contents