YASKAWA Solectria PVI-36TL-480-V2 Installation And Operation Manual
YASKAWA Solectria PVI-36TL-480-V2 Installation And Operation Manual

YASKAWA Solectria PVI-36TL-480-V2 Installation And Operation Manual

Commercial 1000vdc string inverters

Advertisement

Quick Links

Commercial 1000VDC String Inverters
Solectria® PVI 25TL-208
Solectria® PVI-36TL-480-V2
Solectria® PVI 50TL-480
Solectria® PVI 60TL-480
Installation and Operation Guide
Listing File Model:
PVI 25TL-208
PVI-36TL-480-V2
PVI 50TL-480
PVI 60TL-480

Advertisement

Table of Contents
loading

Summary of Contents for YASKAWA Solectria PVI-36TL-480-V2

  • Page 1 Commercial 1000VDC String Inverters Solectria® PVI 25TL-208 Solectria® PVI-36TL-480-V2 Solectria® PVI 50TL-480 Solectria® PVI 60TL-480 Installation and Operation Guide Listing File Model: PVI 25TL-208 PVI-36TL-480-V2 PVI 50TL-480 PVI 60TL-480...
  • Page 2: Table Of Contents

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Document Modification History ........................... 4 Before You Start ................................5 Important Safety Instructions ..........................6 Hazard Symbols ............................. 6 Symbols on Labels ............................7 General Safety Messages ..........................7 Overview ................................
  • Page 3 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Description of the Interface ........................64 Operation State ............................66 Interface Types ............................66 Commissioning ..............................68 Commissioning Checklist ..........................68 Commissioning Steps ..........................69 Menu Functions ..............................72 Fault Shutdown and Troubleshooting ......................
  • Page 4: Document Modification History

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 1. Document Modification History DATE VERSION SECTION MODIFICATION 2022 OCT Creation of document. Labeled DRAFT ECH/HA DOCR version changed from DOCR-071030-A to DOCR-071086-B 2024 JAN Addition of water ingress issues in regards to warranty. Removal of PVI 25TL-208 fuse bypass capability.
  • Page 5: Before You Start

    Be sure to read this manual carefully before using the inverter. Thank you for choosing a Yaskawa Solectria Solar grid-tied PV inverter. This PV inverter is a high performance and highly reliable product specifically designed for the North American Solar market.
  • Page 6: Important Safety Instructions

    PVI 50TL-480 PVI 60TL-480 Please read this user manual carefully before installation of the inverter. Yaskawa Solectria Solar reserves the right to refuse warranty claims for equipment damage if the user fails to install the product according to the instructions in this manual. Failure to follow these instructions and other relevant safety procedures may result in voiding of the product warranty and/or damage to the inverter or other property.
  • Page 7: Symbols On Labels

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Symbols on Labels Table 2-1 Explanation of Symbols on Labels SYMBOL DESCRIPTION DC Signal AC Signal Equipment Ground Phase Refer to Operating Instructions Caution: Risk of Electric Shock Do not remove cover until 5 minutes after disconnecting all supply sources Caution: Risk of Electric Shock Timed Discharge...
  • Page 8 NOTICE! General Damage to Equipment: Attempting to service the inverter improperly may result in damage. Contact Yaskawa Solectria Solar Technical Support for maintenance. Use as Intended: Solectria PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 inverters are designed for PV grid-tied systems. The inverters are to be installed with floating or ungrounded PV arrays only.
  • Page 9 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 interconnection agreement. Placing the inverter into operation before the overall system complies with the national codes, rules and safety regulations of the application is not permitted. If there is a fault;...
  • Page 10: Overview

    The SOLECTRIA PVI 25TL-208,PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 inverters are not intended for use in a micro-grid or off-grid application. Although successful integration into AC-coupled storage systems is possible, Yaskawa Solectria Solar does not support or provide guidance for use in this type of application. Figure 3-1 Grid-Tied PV System...
  • Page 11: Inverter Features

    *positive-fused per 2017 National RSD wiring boxes: 15 positive-fused Electric Code allowance string input positions BIFACIAL MODULES Compatible with Bifacial Modules. Please see Yaskawa Solectria Solar Bifacial Module Application Note. DOCR-071086-C (04/12/2024) Page 11 of 136...
  • Page 12: Inverter Protections

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Inverter Protections OUTPUT MONITORING AC output voltage and frequency monitoring ANTI-ISLANDING Bidirectional frequency perturbation based on Sandia Frequency Shift Detection OVER VOLTAGE PROTECTION Integrated input and output over-voltage protection OVER CURRENT PROTECTION Input and output over-current protection GROUND MONITORING...
  • Page 13: Inverter Diagrams

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 ACTIVE POWER Not Activated Not Activated CURTAILMENT Inverter Diagrams Figure 3-2 SOLECTRIA PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 Inverter Main Items of the Inverter: ①...
  • Page 14 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 19.29in(490mm) 17.83in(453mm) 16.34in(415mm) 12.05in(306mm) 8.97in(228mm) 5.90in(150.00mm) 0.32in(8mm) DC INPUT COMM. PORT 4.29in(109mm) 4.29in(109mm) AC OUTPUT 2.87in(73mm) 2.87in(73mm) Figure 2-4 Wire-box Conduit Knockout Locations ① Knockouts for DC input, (1) 1-1/2 inch Trade Size ②...
  • Page 15: Schematic Diagram And Circuit Design

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 ⑥ DC SPD (Surge Protective Device) ⑦ Internal ground terminal ⑧ AC output terminal block ⑨ Negative DC input busbar ⑩ Rapid Shutdown transmitter Schematic Diagram and Circuit Design The basic electrical schematic diagram of the PVI-36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 inverters with a standard wire box is shown in Figure 3-3;...
  • Page 16 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 voltage by way of opening the PV system disconnect switch, inverter circuit breaker or under loss of grid events, the transmitter stops transmitting the “stay alive” signal sending the MLPE devices into rapid shutdown. This rapid shutdown system has been UL PVRSS listed and compatibility tested and is a certified platform to conform to 690.12 of the 2017 National Electric Code.
  • Page 17: Anti-Islanding Detection

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 WIRE BOX INVERTER POWER HEAD AC/DC Power Transmitter Supply Fuses DC Switch MPPT1 PV1+ PV1+ PV1- PV1- Switch Output Type Ⅲ MOV DC SPD PV1+ MPPT2 PV2+ PV2+ PV2-...
  • Page 18: Dc Arc-Fault Protection

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 DC Arc-fault Protection The inverters include DC Arc-fault detection compliant with UL 1699B-2018. The inverter will detect electrical noise that is indicative of a DC series arc. Upon detection of an arc-fault, the inverter will cease operation. Module-Level Rapid Shutdown The RSD versions of the inverter wire boxes include a SunSpec powerline communication transmitter for use with certain APsmart receivers.
  • Page 19: Labels

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 3-6 Communications Overview Labels The SOLECTRIA PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, AND PVI 60TL-480 has labels on the Power Head. Do not deface these labels as they contain important information required for warranty service. The labels on the Power Head show the inverter specifications and FCC compliance.
  • Page 20: Unpacking

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Unpacking The SOLECTRIA PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 inverters ship in two separate packages, consisting of A) the main inverter enclosure and B) the wire box, mounting bracket, user manual, and accessory kit.
  • Page 21 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Kit contains all necessary Accessory kit hardware and accessories for installation Table 4-2 Accessory Kit ITEM NOTE 4 for securing the wiring box to the main enclosure; 6 for securing the M6 X18mm Phillips inverter to the mounting bracket;...
  • Page 22 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 NOTICE! Maintain NEMA 4X Rating: Water ingress could result in unsafe conditions. Please take note of the following recommendations in order to maintain the NEMA rating and prevent water from entering into the system. •...
  • Page 23: Installation Sequence Overview

    PV power source could cause the inverter to fail and result in a short circuit across the PV array. If the inverter is mounted outdoors without operating power for an extended period of time, Yaskawa Solectria Solar recommends that the inverter power head be inspected for water condensation before any DC or AC power is applied to the inverter.
  • Page 24: Mechanical Installation

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 7. Remove the cover of the Wiring Box. 8. Ensure correct polarity of the PV Strings before terminating the DC source circuits within the Wiring Box. 9.
  • Page 25 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 ambient temperatures near or above the derating temperature of 113°F (45°C), it is best to keep the inverter out of direct sunlight to minimize temperature de-rating and extend product life. Inverter Dimensions The dimensions of the SOLECTRIA PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, AND PVI 60TL-480 inverters are shown in Figure 4-1.
  • Page 26 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 6. The bottom edge of the Wiring Box must remain horizontal (perpendicular to a plumb line). No side-to-side tilting is permitted. Figure 4-2 Inverter Mounting Options Inverter Spacing It is important to allow ample spacing for ventilation, wire management, and service.
  • Page 27 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-3 Inverter Minimum Spacing and Clearance Area NOTICE! The installation clearance between two inverters must be increased to 30 in. when the ambient temperature is higher than 45°C.
  • Page 28 ≥16in (350mm) provided a baffle is installed. Installing an aluminum or galvanized steel baffle (Not supplied by Yaskawa Solectria Solar) with the dimensions detailed above is intended to divert or deflect warm exhaust air from entering the adjacent inverter. Elevated ambient air temperature ≥...
  • Page 29 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-5 Inverter Pillar or Column Mounting Dimensions INFO ✔ If the inverter is installed on a pillar or column (instead of solid wall), the space from the bottom of one inverter to the top of the inverter below may be as small as 11.8in (300mm).
  • Page 30 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-6 Inverter Pillar Mounting Specifications DOCR-071086-C (04/12/2024) Page 30 of 136...
  • Page 31 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Mounting A mounting bracket, shown in Figure 4-9, is provided with each SOLECTRIA PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL- 480, and PVI 60TL-480 inverter. The mounting bracket must be securely attached to a structurally sound, flat surface.
  • Page 32 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-7 Mounting Bracket - Hole Locations DOCR-071086-C (04/12/2024) Page 32 of 136...
  • Page 33 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Referring to Figure 4-9, drill holes at the marked positions with a 10mm (0.4in.) drill and put the M8 expansion tubes, labeled as ①, into the holes; assemble and fasten the mounting brackets, labeled as ②, with the M8x25 assembling bolts, labeled as ③, supplied with the accessory kit.
  • Page 34 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Mechanical Installation, Method Table 4-3 Tools Required TOOL DESCRIPTION NO. 2 PHILLIPS HEAD SCREWDRIVER Torque value of 1.6 Nm (14.2 in-lbs) NO. 10 WRENCH Torque value of 4 Nm (35.4 in-lbs) NO.
  • Page 35 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 CAUTION Heavy Object: The main PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 inverter section is 123.5 lbs (56 kg). Please ensure the mounting bracket is properly installed before hanging the inverter on the bracket.
  • Page 36 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-12 Main Enclosure Cover Plate Remove screws securing the bulkhead cover at the top of the wiring box. Figure 4-13 Wiring Bulkhead Cover INFO ✔ The covers shown above do not have waterproof function.
  • Page 37 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Secure the Power Head to the Wiring Box Secure the wiring box to the main enclosure by using the M6x18 screws (4pcs) to fasten the wiring box (see Figure 4-14 ).
  • Page 38 Figure 4-16 Attach Bulkhead Cover to Wiring Box Anti-Theft Padlock (Optional) The Yaskawa Solectria Solar PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 inverters provide the option to install an anti-theft padlock (not included) when the installation is complete. The anti-theft padlock is used to prevent the inverter from being stolen when the equipment is installed outdoors.
  • Page 39: Electrical Installation

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-17 Location of Anti-Theft Padlock Hole The anti-theft padlock shackle should meet the requirements of the dimensions shown in Figure 4-18. Recommended lock size: A: Shackle diameter 3~6mm B: Shackle width 20~50mm C: Shackle height 20~50mm Figure 4-18 Acceptable Dimensions for Anti-Theft Padlock...
  • Page 40 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Turn the external AC breaker OFF: Verify the absence of AC voltage prior to terminating any conductors. Open Fuse Holders: Verify the absence of DC voltage and current. INFO ✔...
  • Page 41 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-20 Removing the Wiring Box Cover To reinstall the cover, replace cover and align the screws. Use a No. 3 Philips head screwdriver to secure the 4 screws on the cover.
  • Page 42 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 ④ External ground connection point (M6) The internal connection points for the different wiring boxes configurations are shown in Figure 4-22, Figure 4-23, and Figure 4-24. Their different connection points are labeled as follows: ⑤...
  • Page 43 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-24 Internal Connection Points within the RSD Wiring Box (PVI 25TL-208) Figure 4-25 shows the PVI-36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 standard wiring box with the fuse bypass option.
  • Page 44 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Electrical Installation DC The SOLECTRIA PVI 25TL-208, PVI-36TL-480-V2 & PVI 50/60TL-480 inverters provide design flexibility for the installer and designer. The following section provides important information regarding the DC input specifications, wiring requirements, and installation instructions.
  • Page 45 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-26 Independent MPPT Zones Only WARNING Unequal String Lengths and Module Mismatch: Opening fuses under load can cause a hazardous condition. It is strongly recommended to avoid unequal string lengths within a zone and module mismatch. Rapid Shutdown Devices when used, must be used on all MPPTs.
  • Page 46 The SOLECTRIA PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 inverters are shipped with factory installed touch-safe fuse holders and 20 A fuses as factory standard. Ensure that the appropriate fuse values are used for the conductors in the PV source circuit and in accord with NEC 690.9. Yaskawa Solectria does not supply fuses.
  • Page 47 The larger rated fuses may be required for combined input strings; for example, when Y branch connectors are used with DC field wiring to reduce PV source circuit home runs. Yaskawa Solectria Solar allows replacement of the factory installed 20A fuses with appropriate ampere ratings, however Yaskawa Solectria Solar does not provide nor stock these fuses.
  • Page 48 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 inverters. The voltage rating of the fuse must be at least 1000V . In-line fuses can be used for this purpose. Any additional fusing must be installed outside of the inverter.
  • Page 49 The use of the wire ferrules is not mandatory and does not void the product warranty if not used. Ferrules are not provided by Yaskawa Solectria Solar. DC Fuseholder Torque Specification The inverter wiring box may be assembled using fuse holders supplied by either Sinofuse or Mersen (Ferraz Shamut).
  • Page 50 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Using the 1-1/2 inch openings Remove the factory installed liquid-tight plugs from the DC knockout holes in the Wire Box and install 1-1/2 inch Trade Size conduit and conduit fittings. If the use of smaller conduit is desired, use proper weather-tight reducing bushings to ensure the Wire Box maintains its NEMA 4X rating.
  • Page 51 This section includes important information regarding the AC grid connection, wiring requirements, and installation instructions. INFO ✔ String Sizing Tool: Yaskawa Solectria Solar offers a String Sizing Tool to help customers design their PV string sizing at https://www.solectria.com/support/string-sizing-tool/...
  • Page 52 Electrical Code ANSI/NFPA 70 and with all local rules and safety regulations before the inverter can be operated. Yaskawa Solectria Solar PVI line three-phase transformerless inverters prefer a wye configured service with solidly grounded neutral. When needed, a floating WYE or floating delta service is permissible. Please note that when pairing these inverters with a floating WYE or floating delta service, the inverter can only provide DC ground fault detection.
  • Page 53 GridMaxVolt trip point settings. A complete and most up to date guide for transformer requirements can be found in the Application Note: Interconnection Guidelines for Yaskawa Solectria Solar PVI Transformerless Inverters found at: DOCR-071086-C (04/12/2024)
  • Page 54 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 https://www.solectria.com/support/documentation/. The application note interconnection requirements take precedence over the requirements stated in this manual. Neutral Requirements The physical neutral conductor from the inverter to the point of interconnection is optional, but not recommended. It is used by the inverter for voltage sensing only and does not carry current.
  • Page 55 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Use the 1-1/2 inch knockouts Remove the liquid-tight hole-plug from the right side or bottom of the AC input portion of the wiring box to install 1-1/2 inch Trade Size conduit and conduit fittings.
  • Page 56 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-34 AC Output and Ground Cable Connection Table 4-11 Torque and Conductor Specifications CONNECTION POINT CONDUCTOR RANGE TORQUE VALUE L1/L2/L3: AC OUTPUT TERMINAL BLOCK 14.25 N-m (126 in-lbs) -3/0AWG(75/90°C 6 - 3/0AWG (90°C...
  • Page 57 (See the 1st diagram in Figure 4-35) Set up the conductors referring to Figure 4-35. End ferrules and OT type terminals are not provided by Yaskawa Solectria Solar. Figure 4-36 AC Output and Ground Cable Setup When bonding the inverter/mount to a metallic structure is required, use an OT type terminal to connect the ground conductor to the external bonding point at the bottom of the wiring box.
  • Page 58 Table 4-12. Selecting a breaker of another size may either result in nuisance tripping or rejection from the AHJ. Table 4-12 Specification of AC Breaker Selection INVERTER MAXIMUM AC OCPD MINIMUM AC OCPD SOLECTRIA PVI 25TL-208 125A SOLECTRIA PVI-36TL-480-V2 125A SOLECTRIA PVI 50TL-480 50KVA= 80A 125A, suggested 55KVA= 90A SOLECTRIA PVI 60TL-480...
  • Page 59 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 4-38 Preparing Aluminum Wires Prior to Connecting c) Immediately apply a UL listed oxide-inhibiting compound, such as Noalox. d) If the connection is not made within 30 seconds of applying the grease, repeat this process as an oxidized layer may have formed on top of the conductor.
  • Page 60: Communication Installation

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Communication Installation The SOLECTRIA PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 inverters support industry standard Modbus RS-485 communications. The inverters are compatible with the Solectria’s web-based monitoring platform (SolrenView) through the optional Ethernet Network Card.
  • Page 61 A maximum of 32 devices can be connected to this card. When provided with an internet connection, it can send data to an online portal that Yaskawa Solectria Solar can use for troubleshooting and remote diagnostic purposes. As well, customers can opt to purchase access to this portal for easy O&M of their system. It is also used for allowing the connection of a third-party monitoring system.
  • Page 62 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480  Belden 9841, Belden 3106A or Southwire 58164802  UTP CAT-5e or  (3) 18-22AWG communications cables It is recommended that industrial-grade shielded RS-485 cable be used in lieu of unshielded twisted pair. RS-485 communication cables are connected via the 5-pin connector to the port labeled (2) in Figure 4-39.When creating a network of multiple inverters, the cables are terminated to the same 5-pin connector and 3-pin connector.
  • Page 63: Communication Wiring

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 • Use shielded twisted pair as described in 4.4.3. • It is recommended to limit the maximum length of the RS-485 daisy chain to a maximum length of 3000 feet (914 m).
  • Page 64: User Interface

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 termination. Ensure the switch is in the OFF position for all other inverters in the daisy chain, including the one where the Ethernet Network Card is installed. 5.
  • Page 65 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Interpretation for the indicator lights is shown in Table 5-1 and function of the keys is shown in Table 5-2. Table 5-1 LED Indication Meaning LED LIGHT DESCRIPTION Working Power Indicator Light POWER...
  • Page 66: Operation State

    The LCD screen will display different interfaces based on the operation modes of the inverter. There are four operation modes: Logo/Start-up interface, Normal operation, Standby, and Fault mode. (1) Logo/Start-up mode displays the Yaskawa Solectria Solar logo when the inverter is checking if conditions are met for connection after a manual start-up of the inverter.
  • Page 67 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 (2) Indication of inverter operation mode: E-total: E-Today: 24 h Running Status Cycle Display Status Addr:000 2015-10-22 10:00:00 Figure 5-3 Default Display Interface for Normal Operation History Time&Date Error Code...
  • Page 68: Commissioning

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 (4) If the inverter experiences a Fault it will enter Fault mode and display the current or most recent faults. History Record Current Error Running Record Fault Record Figure 5-6 History Record Interface The inverter will disconnect from the power grid and turn into fault mode when the inverter or power grid...
  • Page 69: Commissioning Steps

     You may change the grid standard. The default setting is IEEE 1547. When the inverter completes “sys checking”, the LCD shows the screen as Figure 6-1 below. Press ENTER to the standard selection interface, as shown in Figure 6-1. Yaskawa Solectria Solar Initialization Figure 6-1 System Initialization Logo Setting Language.
  • Page 70 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 The default grid standard is IEEE 1547. If a different standard is needed please go to “Menu Functions” section for further instructions on how to change it. Available grid standards are shown in Figure 6-2.
  • Page 71 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 6-3 Setting the Neutral Line Choosing the communication data. From the previous menu, press ESC to return to the System Parameters menu. Scroll to Communication Setting and press ENT. Select Baud rate and press ENT. The default setting is 9600. Depending on the data acquisition/SCADA system being used, the baud rate may need to be increased or decreased.
  • Page 72: Menu Functions

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480  If the inverter fails to operate normally, the “FAULT” light will illuminate and the fault menu will be displayed. Select Current Error and press ENT to access the current faults the inverter has recorded. This information will show on the LCD screen as shown in the Figure 6-6.
  • Page 73 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 PV Information Independent PV Input Mode PdcTotal(kW) Vdc(V) Idc(A) P1/4 AC Output L1-N L2-N L3-N V(V) I(A) Main Menu F(Hz) Measurement Data Pac(Kw) Setting P Ref 100.0 % Power On/Off PF Ref...
  • Page 74 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Setting Move the cursor to in the main interface. Press ENT, you will be asked for a password. Enter the ETTINGS password: “0000”as shown Figure 7-3. Change the password digits by pressing .
  • Page 75 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Grid Connection Rule IEEE1547 CA Rule-21 HECO-HM HECO-ML ISO-NE IEEE1547_2018 Figure 7-5 G ONNECTION INFO ✔ Please check with your local electricity supply company before selecting the grid standard. If the inverter is operated with a wrong grid standard, the electricity supply company may cancel the operation license.
  • Page 76 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Control Command Control Command Force Restart Time Factory Defaults Vmppt(V) ARC Detect ARC Clear Pmppt(kW) Udc(V) Idc(A) MPPT Scan P2/2 P1/2 Figure 7-6 Control Command Setting INFO ✔...
  • Page 77 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Once this MPPT scan function is activated thru the LCD, it will search the maximum power point at a voltage step of 5V in the MPPT range for full load, and get the maximum power point. Protect Parameters In this interface you can change the Protect parameters of grid voltage, frequency and recovery, etc., as shown in Figure 7-7.
  • Page 78 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 7-1 Protection Submenu Parameters with lower limit, default, and upper limit settings (IEEE 1547-2018 and Rule 21) for the PVI-36TL-480-V2 & PVI 50/60TL-480 and PVI 25TL-208 GRID VOLTAGE PROTECTION SETTING RANGE IEEE 1547-2018...
  • Page 79 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 7-2 Grid Frequency Protection GRID FREQUENCY PROTECTION SETTING RANGE IEEE 1547-2018 RULE 21 ISO-NE PARAMETER NAME DESCRIPTION GRIDFRQMAX1(HZ) Protection threshold 60.00 61.20 66.00 60.00 60.50 66.00 60.00 61.20...
  • Page 80 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 7-3 Grid Recovery GRID RECOVERY SETTING RANGE IEEE 1547-2018 RULE 21 ISO-NE PARAMETER DESCRIPTION NAME Recovery Max 105.00 108.00 108.00 80.00 135.00 80.00 135.00 80.00 135.00 VOLTMAX(%) threshold of grid...
  • Page 81 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 7-4 Grid Voltage Moving Average GRID VOLTAGE SETTING RANGE MOVING AVERAGE IEEE 1547-2018 RULE 21 ISO-NE PARAMETER DESCRIPTION NAME The upper limit grid 100.00 110.00 135.00 100.00 110.00...
  • Page 82 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 7-5 Grid Voltage Balance Grid Voltage Balance Setting Range IEEE 1547-2018 RULE 21 ISO-NE PARAMETER NAME DESCRIPTION 10.00 10.00 10.00 0.01 10.00 0.01 10.00 0.01 10.00 Unbalance rate GRIDVOLBALANCE(%)
  • Page 83 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 LVRT/HVRT LVRT/HVRT menus are used to set the LVRT and HVRT parameters. Move the cursor to this item and press the ENT key to set the parameters. There are 7 pages of LVRT/HVRT parameter settings. These can be changed in the menu tree or by the LVRT (Figure 7-9) and HVRT (Figure 7-10) graphs.
  • Page 84 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 → Through * r a Trip Time/S 2 4 6 8 10 12 14 16 18 20 22 Figure 7-9 LVRT Curve 1.25 Through * r a 1.15 5,6,7,8 Trip...
  • Page 85 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 7-6 LVRT Parameter List with Setup Lower Limit, Default, and Upper Limit SETUP RANGE IEEE 1547-2018 RULE 21 ISO-NE Parameter name DESCRIPTION MIN DEF MIN DEF MIN DEF LVRTVOLT (1,2) (%) Threshold value of Low...
  • Page 86 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 7-7 HVRT Parameters with Setup Range of Lower Limit, Default, and Upper Limit HVRT Parameter name DESCRIPTION IEEE 1547-2018 RULE 21 ISO-NE Threshold value 100.00 125.00 135.00 100.00...
  • Page 87 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 7-8 LVRT and HVRT Parameters (IEEE1547 and Rule 21) LVRT/HVRT SETTING RANGE SETTINGS IEEE 1547-2018 RULE 21 ISO-NE PARAMETER NAME DESCRIPTION 0: Disable 1: Enable, no reactive power LVRTMODESETTING output...
  • Page 88 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Power Derating Setup menu is used to set the active power derating parameters including Active Power OWER ERATING ETUP Derating, Over Frequency Derating, Low frequency derating, and High Temperature Frequency Derating, etc. The parameters are shown in Figure 7-11Error! Reference source not found..
  • Page 89 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 P/W(%) 100% SysFre FreDroop_DbUf(Hz) FreDroop_DbOf(Hz) Freq(Hz) Figure 6-12 Curve of frequency derating Formula for over frequency : +( F +FreqDroop_DbOf- F ) / F / FreqDroop_KOf Formula for under frequency: P = P + (F...
  • Page 90 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 GRID FREQUENCY DERATINIG The dead zone of 0.036 0.036 FREQDROOP_DB over frequency active UF(HZ) power regulation The dead zone of 0.02 0.05 0.02 0.05 0.02 0.05 under frequency FREQDROOP_KOF active power...
  • Page 91 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 ReactivePowerDerating submenu is used to set the Grid reactive power derating parameters including PF EACTIVE OWER ERATING parameters and Q parameters, etc. The parameters are shown in Table 7-10. Press ENT to start the modes after the parameters are set.
  • Page 92 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 (PFCurveP1,PFCurvePF1) Inductive (P%) Capacitive (PFCurveP2,PFCurvePF2) Figure 7-13 PF(P) Curve Mode Curve Table 7-10 Reactive Power Derating Grid Parameters SETTING RANGE PARAMETER NAME DESCRIPTION IEEE 1547-2018 RULE 21 ISO-NE Power of PFPCURVEP1 (%)
  • Page 93 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 3. Q(U) Curve: Use this mode to follow the default or user-specified Q(U) curve. NOTE: The reactive compensation changes according to the grid voltage, as shown in Figure 7-14. Q(%) (QuCurveU2i,QuCurveQ2i) Inductive...
  • Page 94 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Voltage of 90.00 98.00 110.00 90.00 96.70 110.00 90.00 92.01 110.00 QUCURVEU1I (%) Q(U)Curve point 1i Reactive power of -60.0 60.0 -60.0 60.0 -60.0 60.0 QUCURVEQ1I (%) Q(U)Curve point 1i Voltage of 92.00...
  • Page 95 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Q(P) Curve: Q(P) curve mode. Using the curves to set the reactive power setpoints (See Figure 6-16). The reactive power compensation changes according to the active power. Q (%) Inductive QPCurveQ1 )
  • Page 96 Arc Parameters ARC P submenu is used to enable/disable the ARC function and set the ARC parameters. These ARAMETERS settings are only to be changed by Yaskawa Solectria Solar personnel with approval from the AHJ. Setting ARC Bandwith Setting System Parameters...
  • Page 97 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 7-11 Others Submenu Parameters Setup Ranges with Lower Limit, Default, and Upper Limit Settings OTHER SETTING RANGE PARAMETERS PARAMETER NAME DESCRIPTION IEEE 1547-2018 RULE 21 ISO-NE 1200 1200...
  • Page 98 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 1.00 1.00 1.00 0.00 120.00 0.00 120.00 0.00 120.00 DCIPROTECTIONT2 (S) Trip time 2 of DCI PVSTARTUPVOLT (V) PV start-up voltage 3600 5400 3600 5400 3600 5400 MPPTSCANPERIOD (S) MPPTScan Cycle...
  • Page 99 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 NOTICE! Compatibility among the functions: • Only one of these four functions can be valid at one time: QU, PF(P), PF Setting and reactive power setting. LVRT will take priority over the following functions: •...
  • Page 100 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Current Error Date Time Fault 2015/10/22 12:20:08 ArcboardErr 2015/10/22 12:20:08 Fault0040 Fault0040 2015/10/22 12:20:08 Fault0040 2015/10/22 12:20:08 Fault0040 2015/10/22 12:20:08 History Record P1/1 Current Error Running Record Running Record Date Time...
  • Page 101 Figure 7-20 Device Information This menu provides the information to identify the version of boards in the inverter, model number, serial number and data logger information. This information may be required when contacting Yaskawa Solectria Solar service. WARNING Please follow the guidelines below before on-grid operation to eliminate possible dangers and to ensure safety.
  • Page 102 “FAT32” as default. If not, make this selection and click “start.” 2. Obtain a copy of the LCD firmware file and the DSP firmware file from Yaskawa Solectria Solar’s technical support team and copy them into the USB flash drive. The upgrade files need to be placed in the root directory.
  • Page 103: Fault Shutdown And Troubleshooting

    If a fault occurs within the system, the inverter will recognize and report via the LED or LCD panel. If this occurs, reference the following section and serial number of the inverter prior to contacting Yaskawa Solectria Solar for support. This will ensure the quickest time to resolution possible. If the fault is regarding a voltage issue, please...
  • Page 104: Lcd Fault And Troubleshooting

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Table 8-1 Troubleshooting using the LED light indicators LED FAULT STATUS SOLUTIONS 1. Turn off the external AC breaker NEITHER THE 2. Switch the DC switch to “OFF” position “POWER”...
  • Page 105 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 All the installation and wiring connections should be performed by qualified technical personnel. Disconnect the inverter from PV modules and the AC supply before undertaking maintenance. Do not operate or maintain the inverter until at least 5 minutes after disconnecting all sources of DC and AC.
  • Page 106 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 6. Contact the technical support team. Definition: Cooling fan failure Possible causes: 1. Fan is blocked. 2. Fan service life has expired. 3. Fan socket connecter has poor contact. EXTFANERR Recommended solutions: 1.
  • Page 107 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Recommended solutions: 1. Observe for 5 minutes and see whether the alarm will stop automatically. 2. Contact the post-sales technical support team. Recommended solutions: 1. Observe temperature display. WARN0050 (TEMPSENSORER 2.
  • Page 108 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 PROTECTION Recommended solutions: PROTECT0090 1. Restart inverter by turning both AC and DC switches OFF. Wait for (BUS OVER 1 minute for all energy to discharge and turn both switches ON. VOLTAGE) 2.
  • Page 109 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 (OVER- 1. Confirm that external ambient temperature is within the specified TEMPERATURE range of operating temperature. PROTECTION) 2. Check whether the air inlet is blocked. 3. Check whether the fan is blocked. 4.
  • Page 110 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 6. The parameter ISOResist in hidden menu can be adjusted. Check wires of PV and ground: 1. Turn OFF AC switch to disconnect inverter from the grid. 2.
  • Page 111 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 2. Open Fuse holders to isolate PV source circuits. 3. Use meter to find out which PV source circuit is connected in reverse polarity. 4. Correct PV source circuit connection. Recommended solutions: PVXOVERCURREN 1.
  • Page 112 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 1. Check if the logic connector is secured to the Arc board. 2. Run Arc Fault Test from Menu. ETTINGS 3. If Alarm re-occurs, replace arc board or wiring box. FAULT Recommended solutions: FAULT0020...
  • Page 113: Maintenance And Decommissioning Of Inverters

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Recommended solutions: FAULT0100 1. Restart inverter by turning both AC and DC switches OFF. Wait for 1 (GRID RELAY minute for all energy to discharge and turn both switches ON. FAULT) 2.
  • Page 114: Product Maintenance

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Product Maintenance Maintenance is required to ensure that the inverter remains in proper condition, prolonging service life and preventing potential issues. Check Electrical Connections Check all conductor connections during a regular maintenance inspection every 6 months to one year, depending on the temperature fluctuations at the installation site.
  • Page 115 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 50 ~60mm Figure 9-1 Replacing Cooling Fans Figure 9-2 Disconnect the Main Housing from the Wiring Box DANGER Electric Shock Hazard: Please disconnect the electrical connection in strict accordance with the following steps in order to avoid inverter failure or possible electrical shock that could result in death.
  • Page 116 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 The AC breaker of inverter is turned off. • • The DC switch of the inverter is turned off. Afterwards replace the inverter according to the following steps: ...
  • Page 117 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 9-5 Disconnect the Main Housing from the Wiring Box  If the replacement inverter is to be installed immediately, skip this step and refer to section 4.2.5.2 for installation of the inverter.
  • Page 118: Uninstall The Inverter

     Uninstall the inverter by reversing the installation steps found in section 4.2 Mechanical Installation Accessories The Yaskawa Solectria Solar PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, AND PVI 60TL-480 inverters have several optional accessories that allow the inverter to support a wide range of real-world applications.
  • Page 119 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 5. Use a No. 10 wrench to fasten the three pairs of DC input cables to each of the Bypass Terminals at IN1+, IN2+, IN3+ (Figure 10-3) and IN1-, IN2-, IN3- (Figure 10-4) with the M6 screws. Torque value of 50 in-lbs (6.0N.m.).
  • Page 120 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 10-1 Remove Wire Box Cover Figure 10-2 Remove Plastic Touchsafe Finger Guards Figure 10-4 Bypass Terminals Installed on NEG Bus Figure 10-3 Bypass Terminals Installed on POS Input DOCR-071086-C (04/12/2024) Page 120 of 136...
  • Page 121: Shade Cover Kit (Mtlsr-070551)

    Shade covers provide added protection for inverters against harsh environmental conditions like direct sunlight, snow, sleet, ice, hail, and reduce soiling from dust and birds. If the Yaskawa Solectria Solar PVI 25TL-208, PVI- 36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 are to be mounted at any angle lower than 75° from horizontal, a shade cover is required.
  • Page 122 Shade Cover Installation NOTICE! Inverters at 75° or lower: If the Yaskawa Solectria Solar PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 is to be mounted at any angle lower than 75° from horizontal, a shade cover is required. Figure 10-7 Shade Cover Installation; Steps 1 and 2...
  • Page 123 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Install top bracket as shown. Nuts M10- 2 pcs. Torque to 50 in-lbs (5.6 N.m). Install bottom bracket as shown. Screws M6x16- 4 pcs. Torque to 25 in-lbs (2.8 N.m).
  • Page 124: Technical Data

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Technical Data Datasheet MODEL NAME PVI 25TL-208 PVI-36TL-480-V2 PVI 50TL-480 PVI 60TL-480 DC INPUT MAX. PV POWER 45kW (17kW per 61.2kW (22.44kW 90kW (33kW per MPPT) MPPT) per MPPT) MAX.
  • Page 125 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 MODEL NAME PVI 25TL-208 PVI-36TL-480-V2 PVI 50TL-480 PVI 60TL-480 SYSTEM TOPOLOGY Transformerless MAX. EFFICIENCY 97.0% 98.8% 98.8% CEC EFFICIENCY 96.5% 97.4% 98.5% STAND-BY / NIGHT <3W CONSUMPTION ENVIRONMENT ENCLOSURE PROTECTION...
  • Page 126: Measurement Tolerances

    • • ±3% for real-time measurements with output power above 20% nominal power • ±4% for all statistical data Yaskawa Solectria Solar PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, AND PVI 60TL-480inverter tolerances are specified below: • Voltage tolerances: ±1% Current tolerances: ±2%...
  • Page 127: Production Graphs

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Production Graphs The following sections illustrate the inverter production/derating in terms of DC voltage, ambient temperature, altitude and grid voltage. DC Voltage Derating Graph While the Solectria PVI 25TL-208, PVI-36TL-480-V2, PVI 50TL-480, and PVI 60TL-480 inverter has the ability to operate from 200-950 V (Operating Voltage Range), it will only be able to output full rated power for its model from a limited Maximum Power Voltage Range for each model (see graphs).
  • Page 128 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Figure 11-2 PVI-36TL-480-V2 Derating with Respect to DC Voltage DOCR-071086-C (04/12/2024) Page 128 of 136...
  • Page 129 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 PVI 50TL-480 PVI 50TL-480 Figure 11-3 PVI 50TL-480 Derating with respect to DC Voltage DOCR-071086-C (04/12/2024) Page 129 of 136...
  • Page 130 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 PVI 60TL-480 PVI 60TL-480 Figure 11-4 PVI 60TL-480 Derating with respect to DC Voltage DOCR-071086-C (04/12/2024) Page 130 of 136...
  • Page 131 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 High Temperature Derating Graph When the ambient temperature is higher than 113°F (45°C), the inverter output power (Pn) will begin to de-rate, as shown in Error! Reference source not found.. Pin/Pn 100% -3%/℃...
  • Page 132 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Altitude Derating Graph When the altitude is higher than 9842.5ft (3000m), the rated output power (Pn) of the inverter will decrease, as shown in Error! Reference source not found.. Pin/Pn 100% -30%/km...
  • Page 133 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Grid Voltage Derating Graph When the volt-watt function is disabled and the grid voltage is within 100% to ~110% (V to ~1.1*V ) of the Rated Output Voltage, the inverter output power (Pn) may reach 100%. When the grid voltage is lower than the Rated Output Voltage, the inverter will limit the AC Output Current and the output power (Pn) will begin to de- rate, as shown in Error! Reference source not found..
  • Page 134 Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 When the volt-watt function is enabled, the grid voltage is within 100%~106% (V ~ 1.06*V ) of the Rated Output Voltage, the inverter output power (Pn) may reach 100%. When the grid voltage is lower than the Rated Output Voltage or more than 106% V , the inverter will limit the AC Output Current and the output power (Pn) will begin to derate, shown in Figure 10-3-2.
  • Page 135 The Reactive Power Overload function is available for the PVI 50/60TL-480 and is disabled by factory default (Max. AC Apparent Power is 25/50/60kVA and Max. AC Output Current is 69.5A/60.2A/72.2A). For the PVI 25TL-208, only refer to the blue curve. Contact Yaskawa Solectria Solar Customer Service if you want to enable the Reactive Power Overload function.
  • Page 136: Appendix

    Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 36TL-480-V2, PVI 50TL-480 and PVI 60TL-480 Appendix Warranty and RMA Instructions For all warranty information, please visit: http://solectria.com/support/documentation/warranty-information/grid-tied-inverter-warranty-letter/ Datasheet For the most up to date official datasheet, please visit www.solectria.com. Contact Information Telephone 978.683.9700 Technical Support...