YASKAWA Solectria PVI 25TL-208 Installation And Operation Manual page 113

Commercial 1000vdc string inverters
Hide thumbs Also See for Solectria PVI 25TL-208:
Table of Contents

Advertisement

Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 50TL-480 and PVI 60TL-480
 Use a No. 10 Hex wrench to remove the 4 screws between the inverter and the wiring box. Lift the
inverter enclosure and disconnect from the wiring box.
 If the replacement inverter is to be installed immediately, skip this step and refer to section 3.2.5.2 for
installation of the inverter. Otherwise, use a No. 2 Phillips head screwdriver to remove the 2 screws on
the left side of the wiring box, and remove the bulkhead cover. Attach the cover on the connector of
wiring box.
DOCR-071030-A (10/7/2022)
Figure 8-4 Remove the Screws on Both Sides
Figure 8-5 Disconnect the Main Housing from the Wiring Box
Page 113 of 131