Fujitsu FLASHWAVE 7500 Installation Manual page 292

Table of Contents

Advertisement

CHAPTER 4
ETSI Configuration
Checking Power at Optical/Tributary Shelf
11
Is the DMM measurement between –40 and –57 V DC?
If YES:
Go to
Step 12 [p.
If NO:
Report as a trouble item to the installation group and repeat voltage checks after trouble is
corrected.
Repeat the preceding steps for the remaining Tributary shelves.
12
Check the frame ground connections and readings according to local procedures.
13
This procedure is complete.
FLASHWAVE 7500 Release 6.1
4-74
Equipment Installation
Revision 1, June 2009
4-74].
Fujitsu and Fujitsu Customer Use Only
FNC-7500-0061-200
Issue 1, May 2009

Advertisement

Table of Contents
loading

Table of Contents