Fujitsu FLASHWAVE 7500 Installation Manual page 253

Table of Contents

Advertisement

Figure 4-18 [p. 4-35]
Figure 4-18: Flange Mounted on Right Side of SFD6 Shelf (ETSI Rack Installation)
Install the SFD6 shelf in the rack directly above the heat baffle. Secure the shelf to the rack
6
using three rack mounting screws on each side of the shelf.
Note: If hole alignment does not permit three screws on each side, it is acceptable to secure the shelf
with only two screws on each side.
Install the DCM units using the following steps:
7
Locate the appropriate units to be installed and remove them from their protective ESD
a.
packaging.
Loosen the thumbscrews and remove the faceplate/cover from the shelf.
b.
c.
Carefully slide each DCM unit into the appropriate shelf slot.
d.
Replace the cover and tighten the thumbscrews to secure each unit in the shelf.
This procedure is complete.
FNC-7500-0061-200
Issue 1, May 2009
Revision 1, June 2009
shows a right-side view of the SFD6 shelf after the flange is mounted.
Fujitsu and Fujitsu Customer Use Only
CHAPTER 4
ETSI Configuration
Installing the ETSI DCM (SFD6) Shelf
FLASHWAVE 7500 Release 6.1
Equipment Installation
4-35

Advertisement

Table of Contents
loading

Table of Contents