Remove any debris from the area in which the rack will be mounted.
16
Move the rack into position, aligning each of the holes in the base of the rack to the anchors.
17
Install the mounting bolts with lock washers through the equipment rack baseplate and the
raised floor.
18
Install the nuts to the bolts under the raised floor. Tighten them until the lock washers begin
to compress, but do not fully tighten them now.
Secure the top of the equipment rack according to the job specifications. Some equipment
19
racks are secured to existing overhead framework, while others are secured to an adjacent wall
using a horizontal mounting brace. All overhead mounting hardware should be tightened
after assembly.
20
Tighten the floor mounting bolts.
Note: If the rack is installed on a raised floor, there will likely be some type of supports needed.
Instructions for seismic zone installation must also be considered. Follow your local practices for
support and bracing of the rack.
Measure the vertical alignment of the 7-foot equipment rack. Ensure vertical alignment is
21
within 3/16 inch.
Is the equipment rack within the tolerance level specified in
22
If YES:
Go to
Step 27 [p.
If NO:
Continue with
23
Loosen the floor mounting bolts and top mounting hardware, and adjust the equipment rack
using shims on the mounting hardware. All shims and adjustments must meet locally
acceptable guidelines.
Retighten all mounting hardware.
24
Measure the vertical alignment of the 7-foot equipment rack. It must be vertically aligned to
25
within 3/16 inch.
FNC-7500-0061-200
Issue 1, May 2009
Revision 1, June 2009
3-28].
Step 23 [p.
3-27].
Fujitsu and Fujitsu Customer Use Only
CHAPTER 3
Small Configuration
Installing the Rack
Step 21 [p.
3-27]?
FLASHWAVE 7500 Release 6.1
Equipment Installation
3-27

Advertisement

Table of Contents
loading

Table of Contents