VERSION 07/2009
OPERATING MANUAL
6.2.2
ADJUSTING FLUIDIZATION (AIRFLUID)
1
P_01130
ORDER NUMBER DOC 2305835
Procedure:
1. Swivel the feed unit 1 to the right side.
2. Place an opened powder container (25-30 kg;
3. Switch on the control unit..
4. Swivel the feed unit into the powder container
2
5. Adjust the fl uid air at the throttle 2 to the point
Hint:
55.11-66.14 lb) on the vibrator table.
and lower it the surface of the powder. Actuate
the trigger of the spray gun for a short time and
release it. The vibrator motor and the fl uid air
overrun for 10 s (factory setting). This setting can
be changed if required by the user (see opera-
ting manual "EPG Sprint control unit").
that makes the feed unit sink into the powder by
its own weight.
The amount of fluid air depends on the
●
characteristics of the powder.
The powder should be moving in the suction
●
area of the feed unit (gently simmering).
●
Avoid a dust build up in the powder container.