2.3.5.1 SM60A
Step 1: Click the "Enter" button to enter the
menu interface.
Step 3: You will get into the code interface. Then
click the "Shift" button to enter the address
interface.
Step 5: Click the "Enter" button to get back to
the menu interface. Then click the "Shift" button
5 times to enter the save interface.
___________________________________________________________________
Installation
There are 3 buttons on the front of the electricity
meter:
1. Down arrow: shift button
2. Up arrow: value adjustment
3. Enter button / Menu button
Step 2: Click the "Enter" button to input the
password. The initial password is 0000. Then
click the "Enter" button.
Step 4: Please set the meter address by using
the "Value adjustment" button, the Grid meter
(DC, AC and Hybrid system) address is set to
003, and the PV meter (AC and Hybrid system)
address is set to 004.
Step 6: Click the "Shift" button to save the
setting.