GAA610-M ADVANCED EMISSION GAS MONITORING SYSTEM | OI/GAA610-M-EN REV. B
... 6 Installation

Analyzer cabinet installation

CAUTION
Injury hazard due to heavy weight
Depending on the version, the gas analyzer cabinet weighs
approx. 240 kg (529 lb)!
A suitable lifting device (crane, block and tackle, lifting
truck, etc.) is required for transport, setting upright and
installation!
Only use the handling lugs provided to connect any lift
cables to the analyzer cabinet.

Transporting the analyzer cabinet

NOTICE
Potential damage to the device!
Damage to the device due to improper transport.
Use the handling lugs provided to connect any lift cables
to the analyzer cabinet.
The lift cable must be long enough to have an angle of at
least 60° relative to the top of the cabinet when under
tension. If this is not done the handling lugs can be bent or
the analyzer cabinet can be warped.
Figure 22: Lift-Up the analyzer cabinet
Note
It is strongly recommended that the analyzer cabinet is
transported by a specialist firm, transported in a horizontal
position!

Unpacking the analyzer cabinet

1. Lift out the analyzer cabinet from the shipping box.
2. Do not remove the plastic sheet in which the analyzer cabinet
is wrapped. Unpacking a cold analyzer cabinet can lead to
condensation.
3. Remove the plastic sheet only once the analyzer cabinet is at
room temperature. This takes at least 24 hours.

Mounting the analyzer cabinet

Observe the installation site requirements.
The loading capacity of the wall must be high enough to bear
the weight of the analyzer cabinet.
Follow the 'Layout plan' in the drawings set.
The vibration dampers are ready pre-installed. For easy
installation, the upper and lower vibration dampers are each
connected to a mounting plate. See also Dimensions on
page 21.
1. Mount the cabinet with the vibration dampers on the wall
and fix it to the screw holes provided on the mounting plate
using M12 Bolts.
2. Tighten all screws of the analyzer cabinet.
3. Ground the analyzer cabinet by means of the grounding bolt
(grounding cable ≥ 6 mm
Connecting the condensate water drain of
the cabinet air conditioner
NOTICE
Damage to the cabinet air conditioner
Damage to the cabinet air conditioner due to incorrect
connection of the condensate drain and overflow of the
condensate pan.
When connecting the condensate water drain port (TP10)
of the analyzer cabinet air conditioner, observe the
following points:
When routing the drain tube, caution should be taken to keep
it from kinking or being elevated above the exit point of the
air conditioner.
The drain tube must be on a continuous downward slope. A
slight elevation of the tube could result in secondary trap.
2
/≥ AWG 10).