Analyzer cabinet installation
Transporting the analyzer cabinet
Unpacking the analyzer cabinet
Mounting the analyzer cabinet
GAA330-M EMISSION MONITORING SYSTEM
CAUTION
The analyzer cabinet weighs approx. 110 kg. A suitable lifting device
(crane, block and tackle, lifting truck, etc.) is required for transport, set-
ting upright and installation!
Note
It is strongly recommended that the analyzer cabinet is transported by a
specialist firm, transported in a horizontal position as far as possible and
not set upright until immediately before the installation!
Lift out the analyzer cabinet from the shipping box.
•
Do not remove the plastic sheet in which the analyzer cabinet is
•
wrapped. Unpacking a cold analyzer cabinet can lead to condensation.
Remove the plastic sheet only once the analyzer cabinet is at room tem-
•
perature. This takes at least 24 hours.
•
Observe the installation site requirements.
The loading capacity of the wall must be high enough to bear the weight
•
of the analyzer cabinet.
Follow the "Layout plan" in the drawings set.
•
Use only the vibration dampers delivered with the analyzer cabinet.
•
1
Mount the 4 vibration dampers to the wall using M8 bolts or studs.
2
Hang the analyzer cabinet on all 4 vibration dampers simultaneously.
3
Tighten all screws of the analyzer cabinet.
4
Ground the analyzer cabinet by means of the central grounding screw,
route the grounding cable (≥ 10 mm
gland.
|