Installing The Analyzer Cabinet - ABB ACF-NT Installation Instructions Manual

Multicomponent analyzer systems for emission and process monitoring
Hide thumbs Also See for ACF-NT:
Table of Contents

Advertisement

Installing the Analyzer Cabinet

Installing the
Foundation
Unpacking the
Analyzer Cabinet
Setting Up the
Analyzer Cabinet
42/23-571 EN Rev. 5
 Installation site requirements, see
page 8
 Follow the "Layout Plan" in the
system documentation.
 Concrete receptacle with cast-in
M10 bolts or base iron frame with
bores or grating (see the illustration)
CAUTION!
The analyzer cabinet weighs approx. 300 kg.
A crane with a suitable support device is required
for unpacking and handling.
Use the handling lugs provided to connect any lift
cables to the analyzer cabinet.
The lift cable must be long enough to have an
angle of at least 60° relative to the top of the
cabinet when under tension (see the illustration).
If this is not done the analyzer cabinet can be
warped.
 Remove the analyzer cabinet from the shipping box.
Do not remove the plastic sheet in which the analyzer cabinet is wrapped.
Unpacking a cold analyzer cabinet can lead to condensation that will
damage the hygroscopic optical components of the built-in spectrometer.
 Remove the plastic sheet only once the analyzer cabinet is at room temperature.
This takes at least 24 hours.
 Installation site requirements, see page 8
 Material required, see page 13
 Follow the "Layout Plan" in the system documentation.
 Ground by means of the central grounding screw, route the grounding cable
2
( 10 mm
) through the M16 cable gland provided in the left wall of the cabinet.
Installation Instructions ACF-NT, ACF-NT V0309
500
150
800
15

Advertisement

Table of Contents
loading

This manual is also suitable for:

Acf-nt v0309

Table of Contents