APPENDIX B – Device installation and commissioning into ABB Control System
In order to make 266 PdP working with any FF host it is necessary perform some operations as described in the following sections.
The description below is based on the 266 PdP connected to an ABB System but a similar approach is in general valid also for other
non ABB hosts. A summary of the required operations is:
• Off Line Configuration
Importing of the FF device drivers DD&CFF in the host
Design of the FF H1 network
Design of the FBAP
• ON Line Configuration
Assignment of the FF device
Downloading of the FBAP to the H1 network and devices
Device and/or Blocks Configuration.
CAUTION
The first part of the operations is executed in OFF-Line. OFF line means that is not necessary has the real device connected on
the FF H1 network to the host.
Importing of the FF device drivers DD&CFF in the host
The DD&CFF drivers of the 266 PdP FOUNDATION
www.abb.com/instrumentation select the 266 PdP and from the Fieldbus&Hart page download the FOUNDATION Fieldbus EDD/CF
file into a dedicate directory
Then from the Engineering Station of the System (Control Builder) open Libraries and select "insert".
The "Select Capability File" window is opened and from its browser search the downloaded 266 PdP Capability File (CFF) in the
hard disk. Once it has been found press "Open".
Fieldbus have to be previously downloaded from the From the ABB web-site,