Note: Before removing the electronic expansion valve, make sure there is no refrigerant in the pipeline and power is cut off.
Step
5. Install the new electronic
expansion valve.
6. Secure the electric box and
arrange the wires as required.
7. Check and install the panels.
Removal of electronic expansion valve
Picture
116
U-Match 5 SERIES UNIT SERVICE MANUAL
Weld the connection pipe of
electronic expansion valve.
When welding the electronic
expansion valve, the valve
should be wrapped with wet
cloth.
Nitrogen welding: the pressure
of nitrogen is 0.5±0.1kgf/ c ㎡
(relative pressure).
Note: When welding the pipes,
do not let the flame burn the
other components.
Install the coil of electronic
expansion valve.
Put the electric box back in
place and tighten up the
screws.
Arrange the wires as original.
Check whether each
component and connection
wire is well connected.
If everything is OK, install the
upper, left and right panels.
Tighten up the screws.