Installation Activity and Test Sequence

Installation and test operations for SLC
outlined in this text as sequential procedures. For ease of operation, it is
recommended that the format and sequence listed herein be followed. Common
mechanical-type instructions and information are outlined in Chapter 2,
Installation Procedures.
The installation sequence for a SLC -2000 route may begin either at the central
office, remote locations, or simultaneously at any combination of offices,
depending upon the availability and deployment of personnel. The installation
operation is considered complete when all bays are interconnected with the cable
or fiber line facilities, and with the power, ringing and alarm systems.

Remote Terminal

Installation consists of the assembly, functional wiring, peripheral cabling, and
peripheral powering of the 7-foot SLC -2000 RT bays. Also included are the
peripheral equipment, such as the ringing supplies and their associated
interconnections.

Wiring Operations

Preparation of the cable assemblies (VF, T1 lines, and alarms) involves wiring the
customer's cables to the furnished connectors, which mate with the SLC -2000
Access System equipment shelf connectors. This cable preparation may be
performed independently of other installation activity. If this work is done in
advance or simultaneously with the site preparation activity, the overall
installation interval may be reduced.