Hot Commissioning By Drivestartup; Close Mcb And Load Power Module Software; Cooling And Heating System Testing - ABB ACS580MV Commissioning Manual

200kw to 6300 kw,3.3kv to 11 kv
Hide thumbs Also See for ACS580MV:
Table of Contents

Advertisement

1. Check all the control cables have been assembled according the customer interface
drawing.
2. Select the type of connection to overriding system in DriveStartup: Standard IOs,
External module IOs or Fieldbus.
3. Check the configuration in below parameter settings:
Group 19 Operation mode
Group 20 Start/stop/direction
Group 22 Speed reference selection
Group 82 Charging/MCB control
Group 10 Standard DI, RO
Group 12 Standard AI
Group 13 Standard AO
Group 14/15/16 I/O extension module 1/2/3
Group 51 FBA A settings
Group 52 FBA A data in
Group 53 FBA A data out
Group 82 Charging, MCB control
4. Set the parameters as required and check the signals are correct sent and received
between the drive and overriding system.

Hot commissioning by DriveStartup

After completing the tasks in the previous chapters, the converter can be energized.
DANGER From this step MCB is in normal position and controlled only by
ACS580MV. Medium voltage can be connected to the converter! Confirm
safety area of motor is cleared and auxiliary equipment of motor is in operation.

Close MCB and Load Power Module software

After MCB has been closed and medium voltage introduced to the converter, power
modules (PMs) boot up.
BCON controller checks the SW version to each PM.
If all PMs don`t have the same version or if the PM SW version is outdated BCON will
initiate SW downloading to PMs.
Due to safety reasons, during SW update MCB will be open (fault 607E "PM software
update in process" is active).
The fault cannot be reset until the SW update is finished (this is indicated by another fault
message: 607F "PM SW update done").
Please operate the converter according to the description of "DriveStartup".

Cooling and heating system testing

Check the configuration and feedback signals of the cooling fans. Group 87 Cooling
system, parameter 17.5/87.40 INU/TRU fan feedback.