106 Option
3. Phase order of main supply (MB input side) must be clockwise. The synchronization is
only possible if the drive run the motor with a clockwise rotating field. If the motor has
to run anti clockwise the phase order has to be changed directly at the motor.
Overview of installation work and check list
•
Mechanical installation was completed.
•
SBU and MAU free of pollution due to installation.
•
Power supply and signal cables for fans in transformer unit.
•
Converter control power supply must be 1-phase 230VAC.
•
Before closing the control power supply circuit breaker in MAU, measure the incoming
auxiliary supply voltage and verify that it is within +/-10% of its nominal value.
•
Auxiliary power, ground, control and serial communication cables made properly.
•
Options (cabinet heater, CP610, etc.) supply cabling properly made.
•
Power cables for SBU functions are made and installed properly (including converter
output to MSS, MSS to motor, MB to motor, grid to MB).
•
Interface cables for SBU function (control device to ACS580MV) are properly made.
Insulation test
The insulation test is not recommended, if necessary check the description in
Resistance
Measurements.
Download software
Marshalling PLC software
Marshalling PLC is optional, just for multi motor mode. As
DriveStartup
described, take the loading package for the latest software release and
download to Marshalling PLC using thes same procedure as to AC500 of ACS580MV.
Loading software and prepare
Insulation