78 Standard Commissioning Process
Observe and save the measurement, attach plot to report.
If the motor rotates in the opposite direction correct the motor cabling or change the
parameter 99.16 Phase order to UWV.

Fly start

If flystart is required by the project, do the below test, otherwise skip this step.
Take the drive to Local control by DriveStartup, select online mode.
Save and set following parameters:
a. 21.19 Scalar start mode to Automatic
b. 21.03 Stop mode to Coast
Set the speed reference to motor rated speed and start the motor. When motor
reaches the set point stop it and restart nearly 10s later.
Repeat the steps at different points as required, confirm the motor can be well found
and controlled.
Observe and save the measurement, attach plot to report.