82 Standard Commissioning Process
Motor speed ramp up
a. Set the speed reference to motor rated speed in drive control toolbar.
b. Start the motor and observe the related signals, compare the current with parameter
30.17 Maximum current.
Motor speed ramp down
a. Set the speed reference to 0 in drive control toolbar.
b. Observe the related signals, compare the DC voltage with parameter 30.54
Overvoltage limit. Stop the motor.
If above conditions are fulfilled the requirement, repeat both tests 3 times.
If not fulfilled the requirement, check the below parameter setting.
a. Parameter 21 Start/Stop mode
b. Parameter 23 Speed reference chain
c. Parameter 28 Frequency reference chain
Observe and save the measurement, attach plot to report.
Run the motor for a while from customer control while you fill in the paperwork.

Vector Control

Before doing vector control related test, configure the drive as normal with scalar control
mode according to normal service configuration process. Check that the drive can run the
motor normally.
Set control mode to vector. Parameter 99.04 for setting Motor control mode.
Calculation of asynchronous motor parameters. For precise vector control
performance, it is recommended to get motor 1-ph equivalent circuit diagram.
Nameplate data could be used as a workaround.