This chapter provides information on pre-commissioning check lists.

Office preparation check list

In order to achieve an efficient commissioning, make sure that the following items are
completed before traveling to site:
Field service report template
Programing software tools and DriveStartup software tool
Copies of converter documentation (commissioning manual, wiring diagrams,
mechanical drawings and publications as per
Information on the scope of delivery
Information on latest SW and parameter updates (contact MV Drives Supportline)
Information on possible converter upgrades
Setting values for motor parameters
Commissioning program (to be agreed with customer)
Suitable megger for insulation test if necessary