100 Option
Insulation test
The insulation test is not recommended, if necessary check the description in
Resistance
Measurements.
Commissioning for MBU=0001 option
•
Confirm the MCB has been racked out and grounded.
•
Ground the input busbar in TRU cabinet by grounding harness for safety.
•
Connect the control cables among the MCB, MBU and COU cabinet.
•
Disable the local close push button on MCB cabinet.
•
Connect the auxiliary control power supply to the cabinet.
Check of the isolation switches position
•
Follow the operation sequence, operate the switches of QS1(Q1), QS2(Q2) and
QS3(Q3).
Insulation