100 Option

Insulation test

The insulation test is not recommended, if necessary check the description in
Resistance
Measurements.

Commissioning for MBU=0001 option

Confirm the MCB has been racked out and grounded.
Ground the input busbar in TRU cabinet by grounding harness for safety.
Connect the control cables among the MCB, MBU and COU cabinet.
Disable the local close push button on MCB cabinet.
Connect the auxiliary control power supply to the cabinet.
Check of the isolation switches position
Follow the operation sequence, operate the switches of QS1(Q1), QS2(Q2) and
QS3(Q3).