86 Standard Commissioning Process
Safety training
Overview of the system and cabinet
Door interlocking system
Control panel
a. Reading and interpreting status, alarm and fault messages
b. Control modes (local/remote)
Energizing and starting the converter
Stopping and de-energizing the converter
General maintenance work
Exchange the power modules
Install the Drive composer entry
a. Save the parameter file and event logger
b. Monitor the graph
c. Create the support package
Copy the SD card date from the drive
Standard troubleshooting process and where to get help

Customer approval

After the test runs have been performed and the Commissioning Report has been filled in
completely, the representative of the customer is asked to confirm the end of the
commissioning with his/her signature on the report.
Date and signature on the report will indicate the beginning of the warranty period to the
factory.

Create the commissioning report

Complete all the steps of commissioning work. Remark all the details uncompleted and
inform the project manager and MV Drives Supportline.