86 Standard Commissioning Process
•
Safety training
•
Overview of the system and cabinet
•
Door interlocking system
•
Control panel
a. Reading and interpreting status, alarm and fault messages
b. Control modes (local/remote)
•
Energizing and starting the converter
•
Stopping and de-energizing the converter
•
General maintenance work
•
Exchange the power modules
•
Install the Drive composer entry
a. Save the parameter file and event logger
b. Monitor the graph
c. Create the support package
•
Copy the SD card date from the drive
•
Standard troubleshooting process and where to get help
Customer approval
After the test runs have been performed and the Commissioning Report has been filled in
completely, the representative of the customer is asked to confirm the end of the
commissioning with his/her signature on the report.
Date and signature on the report will indicate the beginning of the warranty period to the
factory.
Create the commissioning report
Complete all the steps of commissioning work. Remark all the details uncompleted and
inform the project manager and MV Drives Supportline.