Protection Relays - ABB ACS580MV Commissioning Manual

200kw to 6300 kw,3.3kv to 11 kv
Hide thumbs Also See for ACS580MV:
Table of Contents

Advertisement

Protection relays

ACS580MV with integrated transformer
The protection relays in the feeding switchgear for the converter's transformer must be
commissioned and tested as per the manufacturer's documentation.
The settings for the protection relay are defined by the protection or system engineer. The
commissioning engineer should only verify these values.
Relay test protocols must be available on site before the drive is energized.
NOTICE The below mentioned settings are just informative for the commissioning
engineer, in which range the protection settings should be made. The customer is fully
responsible for the protection settings.
A protection curve can be programmed into the relay. The protection curve defines how
long a current of a certain magnitude is allowed to flow until the relay opens the MCB.
There are three types of protection modes:
Instantaneous
Short delay
Time over current protection
The recommend protection functions and setting values:
Protection functions
Immediate overcurrent trip level
Short time delay overcurrent trip
level
Long time delay protection pickup
level
Transformer protection modes
Setting value
10 times the rated current of the
ACS580MV
2 times the cable rated current with
500ms delay
1.3 times the rated input current of the
ACS580MV
Standard Commissioning Process 27