94 Standard Commissioning Process

Customer documentation

The following documentation stays with to the customer after the commissioning:
Copy of the commissioning report.
Copy of the parameter backup files:
a. .prn (txt) file, customer access level
b. .dcparamsbak file, service access level
Copy of the signal and parameter table in electronic format
Note: Make sure that the correct version stays with the customer.
Copy of modified parts list, mechanical and electrical drawings if any.

Documentation and backup copies to MV Drives Supportline

For revising and archiving of the factory documentation and for later assistance of the
customer send the following to the MV Drives Supportline:
Copy of the commissioning report (MoR database)
Copy of the field service report (MoR database)
2UBB021641_ACS580MV Drive and Site Condition Check List' (MoR database)
Copy of the parameter backup files (MoR database):
a. .prn (txt) file, customer access level
b. .dcparamsbak file, service access level
SD card data (MoR database)
Copy of modified parts list, mechanical and electrical drawings if any.
Warranty report(s) of replaced components if any.

Duration and description of commissioning

The time schedule describes a typical ACS580MV commissioning (excluding special
options like synchronized bypass etc.). To be able to follow the schedule, the preconditions
must be fulfilled. Commissioning of the drive must be done by a certified engineer.