Step 3:
Next, an interjection of a "Logic Element" needs to be inserted into the freshwater pump circuit
control. Find out what type of "Input Signal" is currently being used for the freshwater pump
load. In this case it is "Network Input 4". Remove "Network Input 4" and add an available "Logic
Element". In this example we are going to use "Logic Output 4". Ensure "Toggle Mode" is Off
as "Toggle Mode" changes the state of the breaker every time and "Input Signal" is detected
therefore this will cause the pump not to restore its state when the tank is re-filled. Also
because we do not want to allow for direct ECB control accessibility, turn "Manual Mode" on.
From:
CLMD16 Configuration Guide Rev.1.1
33