Installation
24
3.4
Post-installation check
Perform the following checks after installing the measuring device in the pipe:
Device condition and specifications
Is the device damaged (visual inspection)?
Does the device correspond to specifications at the measuring point, including
process temperature and pressure, ambient temperature, measuring range, etc.?
Installation
Are the measuring point number and labeling correct (visual inspection)?
Is the orientation chosen for the sensor correct, in other words suitable for sensor
type, fluid properties (outgassing, with entrained solids) and fluid temperature?
Process environment / process conditions
Have the inlet and outlet runs been observed?
Is the measuring device protected against moisture and direct sunlight?
Is the measuring tube properly secured against vibration (fasteners,
support)?
Proline Prosonic Flow 93C FOUNDATION Fieldbus
Notes
–
→ ä 5 ff.
Notes
–
→ ä 14 ff.
Notes
→ ä 15
–
→ ä 15