Start-Up Checklist

1-6 | Thermox Series 2000 WDG Insitu Analyzer
Review the Installation chapter (Chapter 3).
Install the sensor on the process
-
If the sensor is on a pipe nipple, insulate the pipe from the process
wall to the mounting flange of the sensor.
Install the control unit.
-
Do not create any additional conduit entries in the enclosure.
Interconnect the control unit and the sensor as shown in the intercon-
necting drawings.
-
The specified cable must be used to ensure proper operation of the
system
-
Keep the interconnecting located in the control unit as short as pos-
sible. You do not need to use a service loop.
-
Maintain the ordered wire pairs as shown in the drawings.
Connect the AC mains supply to the control unit and the sensor. Make
sure that the AC voltage is within specified limits.
Configure your analyzer as explained in Chapter 4 - Controller/User
Interface.
Calibrate your system as described in the Chapter 5 - Calibration.