Crane Care
8
Load hoist mechanism
8.1 check the pressure roller on the winch
Personnel
Service Technician
The machine operator
Safety precautions
Screw tightening torque in Nm
Quality
M6
M8
8.8
10
23
10.9
14
34
12.9
16
40
8.2 Check the limit switch on the winch
Personnel
Service Technician
21.12.2017
Interval
Particular interval: before/after long usage periods,
The winch pressure roller is pre-tensioned. There is a risk of
n
clamping. Ensure that the winch is disconnected from power
and prevented from switching back on during work on the pres-
sure roller.
Only work on the winch when the machine is off and not under
n
load.
Protective equipment:
Special tool:
1.
Check if the springs installed are pressing the pressure roller
into the rope in the drum direction.
Check
2.
n
n
M10
M12
M14
46
79
125
67
115
185
79
135
220
Interval
Particular interval: every 100 OH
Preliminary
GHC75 Telescopic crane
Protective clothing
n
Safety goggles
n
Hard hat
n
Protective gloves
n
Fall arrest safety harness
n
Spanner
n
if the pressure roller locking screws' counter nuts have
loosened due to operational vibrations.
if the sheave turns freely.
M16
M18
M20
195
280
395
290
400
560
340
470
660
Load hoist mechanism
Check the limit switch on the winch
M22
M24
540
680
760
970
890
1150
M30
1350
1950
2300
79
Need help?