5.12. THREE PLATFORM DECK CORNER CLOSURE
The three platform deck corner closure is required wherever three platforms are assembled in an
inside corner, regardless of whether the corner includes a closure, guard, or two-line rail.
5.12.1. After assembling the platform picketed guards or two line rails (or other closure
FIG. 5.52
PATHWAY HD Code Compliant Modular Access System Installation Manual
component if present), but before any of the handrail components, install a platform
angle post in the open corner pocket at the corner (FIG. 5.52) and secure in place in
the same manner as described in 'ASSEMBLE TWO-LINE PLATFORM RAILS AND
PICKETED GUARDS' section.
Page 72 of 92
Need help?
Do you have a question about the PATHWAY HD Code Compliant Modular Access System and is the answer not in the manual?