3.1.2 Clearances for SED2 of the IP20 range
The IP20 range of SED2 units can be mounted side by side without space in between. Keep the following minimal
clearance above and below the VSD for the movement of cooling air:
≥
100 mm
SIEMENS
SIEMENS
SED2
SED2
≥
100 mm
3.1.3 Drilling plan for SED2 IP54
W
5192M02
10 / 100
Siemens
Building Technologies
Frame size
A, B, C
D, E
F
Frame
size
B
C
D
E
F
Commissioning Guide
3 Mechanical installation
Min. vertical clearance V
in mm
100
300
350
Spacing
Mounting material
H
W
(mm)
(mm)
4 x M6 screws
4 x M6 nuts
342.8
230
4 x M6 washers
4 x M6 screws
4 x M6 nuts
564
312.7
4 x M6 washers
4 x M8 screws
4 x M8 nuts
647
310
4 x M8 washers
4 x M8 screws
4 x M8 nuts
847
310
4 x M8 washers
4 x M8 screws
4 x M8 nuts
1112
400
4 x M8 washers
min.
Tightening
torque
5 Nm
5 Nm
13 Nm
13 Nm
20 Nm
CM1G5192en
29.07.2010