Chapter 6
Unpacking and checking the devices
Required documents
Chapter 6
Unpacking and checking the
devices
Before unpacking devices, check whether the packages are intact. Have the project
supervisor be present during the unpacking process.
When unloading the devices, place the packages in order with the labels on the
packages facing the same direction.
1.
Unload the devices.
2.
After the devices are unloaded, check whether the quantity of packages received
matches the shipping documentation.
If yes, execute Step 4.
If no, execute Step 3.
3.
The project supervisor should complete the Cargo Inspection Feedback Form
signed by the customer to the local office within three days.
4.
Check whether the packages are intact and whether the packages have been
upside down during transportation.
If the packages are severely damaged or wet, execute Step 7.
5.
Check the Shock Watch label which is attached to the shipping container. If the
indicator is red, execute Step 7.

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the NetBackup 5220 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

This manual is also suitable for:

Storage shelf

Table of Contents