Installing an Avaya MCC1 Media Gateway
Install Auxiliary Cabinet Equipment
The auxiliary cabinet allows for carrier, 23-in. (58.4 cm) rack, or panel mounting of the
hardware. The following equipment is furnished with the media gateway:
•
Fuse panel
•
Power receptacle strip
DC connector block
•
DC source
AC to DC power supply
•
switched outlet to the required DC voltage.
Install equipment inside the media gateway as specified in the CSD. The following optional
equipment can be installed:
909A/B Universal Coupler
•
•
Fan Assembly
External Channel Service Unit (CSU)
•
•
PagePac Paging System
power.
External system announcement units -- may be powered by either -48V DC or 120 VAC.
•
Install Earthquake Protection for Media Gateway
Use the correct procedure for your installation:
''Install Concrete Floor Mounting'' on page 68
•
•
''Install Raised Computer Floor Mounting'' on page 69
Install Concrete Floor Mounting
Position the media gateway in the exact position it is to occupy when the installation is
1
complete.
Insert a pencil or marker through the holes previously occupied by the carriage bolts
2
(front and rear) in the bottom of the media gateway and mark the floor directly beneath
each hole.
Roll the media gateway out of the way and drill four 1/2-in. (1.27 cm) diameter holes
3
about 1.5 in. (3.8 cm) deep at the locations marked in Step 2.
Insert concrete floor anchors (STARR part number 3425) into the holes.
4
—
Distributes -48 VDC power to fused cabinet circuits
—
Provides switched and un-switched 120 VAC receptacles
—
Required when the auxiliary cabinet is powered by an external
—
Converts AC power provided by the AC power strip
—
Requires 120 VAC power
—
3 models are available. All PagePac models require 120 VAC
October 2002
—
1 is required for each T1 carrier link