To prevent serious injury, only operate Reactor
with all covers and shrouds in place.
NOTICE
Proper system setup, startup, and shutdown
procedures are critical to electrical equipment
reliability. The following procedures ensure steady
voltage. Failure to follow these procedures will
cause voltage fluctuations that can damage
electrical equipment and void the warranty.
1. Check generator fuel level.
Running out of fuel will cause voltage fluctuations
that can damage electrical equipment.
2. Check coolant levels.
Inspect the level of coolant inside the engine
coolant expansion bottle (EB) and heat
exchanger coolant expansion bottle (HB).
332636C
T
H O
L D
C O
3. Check fluid inlet filter screens.
Before daily startup, ensure that the
fluid inlet screens are clean. See
Flush Inlet Strainer Screen, page
4. Check ISO lubrication reservoir.
Check level and condition of ISO lube daily. See
Pump Lubrication System, page
5. Confirm main power switch is OFF before starting
generator.
Startup