Installation Planning; Physical Space; Time And Personnel - Oracle StorageTek SL3000 System Assurance Manual

Hide thumbs Also See for StorageTek SL3000:
Table of Contents

Advertisement

This chapter outlines requirements and planning considerations for an SL3000 library
installation.

Physical Space

Time and Personnel

Shipping Weights and Measures
Pallet Double Stacking
Installation Tools
Physical Space
A successful installation of the SL3000 library requires an adequate physical space. For
dimensions of the library modules, see
page 7-2. If modules will be added in the future, ensure there is enough room to
expand the library.
Floor
Ensure that the weight and coplanar requirements are satisfied (see
Requirements"
Transportation
If the equipment must be transported on elevators, the elevator cars must be capable
of safely handling the weight. Additionally, ensure that the components can pass
through doorways and fit in elevators. For more information, see
and Measures"
Construction Area
The minimum working area (not including the space required for the pallets) is
approximately 19 m
Waste Disposal
Sales and service personnel should plan with customers on the disposal of all packing
material. Determine if waste bins or recycling containers will be provided on site or
whether an independent company will handle the disposal at additional cost.
Time and Personnel
The table below shows the estimated times for the installation of modules and
components. At least two qualified service representatives should install the library.
The times listed below do not include library initialization, testing, audits, and feature
on page 7-5).
on page 8-2.
2
2
(200 ft
).

Installation Planning

8
"Physical Dimensions and Weights"
8
on
"Floor
"Shipping Weights
Installation Planning 8-1