5 Maintenance
5.1 General
5.2

User maintenance schedule

Table 5.1 provides a guide to maintenance operations and intervals at which these op-
erations should be performed by the user. The user is however responsible for deciding
the type of operations and length of intervals necessary to maintain system function
and safety.
44
WARNING
Do not perform any type of maintenance work while the system is
powered electrically or when the piping system is pressurized. Note
that the piping system can be pressurized even when the system
is closed down.
WARNING
When using hazardous chemical and biological agents, take all
suitable protective measures, such as wearing protective glasses
and gloves resistant to the substances used. Follow local and/or
national regulations for safe operation and maintenance of
ÄKTAprime plus.
CAUTION
Fire hazard. Follow instructions in ÄKTAprime plus Operating
Instructions for correct installation of a new UV-lamp. If the lamp
is not installed properly it may be overheated and cause a fire
hazard.
NOTICE
Cleaning. Keep the instrument dry and clean. Wipe regularly with
a soft damp tissue and, if necessary, a mild cleaning agent. Let the
instrument dry completely before use.